Summary
The Centre for Sustainability (CS) is proud to report on its Saving the Almaciga Tree project (execution October 2014- August 2016), as part of its efforts to establish the Cleopatra’s Needle Forest Reserve (CNFR). The Almaciga tree is the primary non-timber forest product of the forests of Cleopatra’s Needle – its high-value resin represents approximately 80% of the income of the Indigenous Peoples (IPs) who have lived in this area since time immemorial. This ancient coniferous tree used to dominate the forests of northern Palawan—over-harvesting, together with illegal activities, now threaten its existence. The indigenous communities in the area together with CS aim to ensure the future of the Almaciga tree, and thus livelihood and existence of the IPs, through research, reforestation, and education & training.
Upon completion of this project in August, 2016, CS is proud to report that it has achieved all of its original objectives as per the initial proposal, namely:
- Reforestation of the proposed CNFR with 5077 Almaciga seedlings propagated by Indigenous and local communities from the first-ever Almaciga cone-based propagation nurseries in the Philippines.
- 3 ground-breaking scientific reports documenting a baseline survey of the population & health status of the Almaciga tree in the proposed CNFR; a baseline survey of the current overharvesting practices of the Almaciga tree occurring in the proposed CNFR; and a nursery protocol for Almaciga tree propagation.
- Execution of community trainings and workshops, in Almaciga propagation & reforestation, sound resource management & planning, awareness-raising of current Almaciga tree status & sustainable harvesting techniques, and inter-IP exchange for better governance & resource management
- Execution of Environmental Education Program (EEP) in 11 elementary schools.
These achievements were made by overcoming the following difficulties:
- Philippine bureaucracy proved to be the primary challenge which affected all aspects of the project. The delays caused by the consultation & consent process to work with the IPs of the project area ultimately meant that only 1 of the 4 Indigenous communities could fully benefit from the project. In addition, research could only be carried out in 4 of the 7 Barangays of the project area. The delays caused by the consent process to work with the elementary schools also meant that 1 out of the 11 schools was not able to participate in the EEP.
- The delay in initial release of funds for this project meant that we missed the cone collection season of 2014 (August-September, annually). We subsequently had to wait another 10 months after project commencement to start Almaciga propagation activities.
- The weather conditions brought on by El Niño 2016 meant that Reforestation was further delayed by one month, further extending the project timescale.
This project is made possible with the generous support of Fauna & Flora International United Kingdom (October 2014-August 2016) and the Philippine Tropical Forest Conservation Foundation (PTFCF – July 2015-August 2016).
By: Karina May Reyes-Antonio